Building a forever home on South-Island soil is a marathon, not a sprint. Between rugged coastlines, layered municipal regulations, and the increasingly stringent BC Energy Step Code, the schedule for a Greater Victoria custom home build can feel like a puzzle. The good news? With a transparent roadmap - and a construction partner that has run this race many times - you can predict the pace with surprising accuracy. Below, the Stillwater team breaks down every phase, explains local permit timelines, and shows how our “Stillwater Experience” keeps projects moving while elevating sustainability at every turn.
Pre-Construction Planning & Design (≈ 2 – 4 Months)
Introductions: We Listen.
Every project starts with a long coffee and a lot of questions. We unpack lifestyle goals, future-proofing ambitions, and energy-use targets so the design never outruns the budget. By listening first, we eliminate “re-work” later - one of the biggest causes of blown timelines.Pre-Construction Services: We Dream & Plan.
Alongside your architect and our team of consultants, we investigate zoning restrictions, geothermal potential, solar orientation, and prevailing winds. Early energy-modelling helps us decide whether triple-glazed windows, thicker wall assemblies, or a hybrid heat-pump system will deliver the best return on comfort and carbon savings. By the end of this stage we’ve produced concept drawings, a line-item budget, and identified risks so everyone sees the potential roadblocks before they appear.
Financing & Cost Alignment.
Lenders love clarity. We refine allowances for big-ticket items - windows, cabinetry, renewable systems - early, so financing packages can be locked in before permits land. Sustainable elements such as heat-pump water heaters or rooftop photovoltaic arrays often qualify for green-home rebates, creating wiggle room in the budget without adding time.
Permitting & Municipal Approvals (≈ 2 – 6 Months)
Greater Victoria isn’t a single jurisdiction. Between the City of Victoria, Saanich, Oak Bay, Langford, North Saanich and the Gulf Islands, etc., each municipality has its own checkpoints and queue lengths. Here’s how the milestones stack up:
Permit Type |
Typical Duration |
Why It Exists |
How Stillwater Speeds It Up |
Standard Building Permit |
6–12 weeks |
Confirms structural & Step Code compliance |
Pre-flight checklists catch missing data before submission |
Development Variance Permit |
~10-16 weeks |
Allows front-setback tweaks, added height, or suite additions |
Bundle variance requests so every department reviews once |
Heritage Alteration Permit |
3–4 months |
Protects registered heritage façades |
Upfront consultations with heritage planners shorten back-and-forth |
Tree / Environmental DP |
1–3 months |
Safeguards shorelines & mature Garry oaks |
Arborist reports & rain-garden plans are included in the first package |
Sustainable edge.
Submitting a robust energy-model and tree-protection plan signals to planners that you’re delivering community benefits, not just square footage. Approvals tend to flow faster when the project clearly exceeds minimum code.
Site Preparation & Foundation Work (≈ 1 – 2 Months)
Mobilization & Clearing.
We start by erecting silt-fencing, tree-protection zones, and storm-water controls, preventing runoff into salmon-bearing streams. Salvageable timber is milled off-site for use in accent walls or exterior detailing.
Excavation & Rock Removal.
Vancouver Island bedrock can be stubborn. Geotechnical scans help us decide whether controlled blasting, rock-socketed piles, or stepped footings will minimize disturbance. Spoil rock is crushed for use as driveway base - less trucking, less carbon, lower cost.
Foundation Forming & Pour.
Insulated concrete forms (ICFs) or slab-on-grade with under-slab insulation create a thermal break that keeps conditioned air inside where it belongs. Coastal moisture and cooler temps demand longer curing; using fly-ash-blended concrete reduces cement demand by up to 30 percent.
Framing & Building Envelope (≈ 2 – 3 Months)
Stick-Built vs. Panelized Framing
For remote Gulf Island sites, panelized wall systems are pre-built in a climate-controlled facility, then barged over. Walls arrive square and straight, shaving two to three weeks off the schedule and reducing waste by up to 50 percent.
Lock-Up Milestone.
Hitting “weather-tight” by week 10 lets interior trades work regardless of rain. We install high-performance membranes, over-insulated headers, and taped sheathing seams that reduce air leakage to Passive-House levels - future-proofed against stricter Step Code tiers.
Mechanical, Electrical & Plumbing Rough-Ins (≈ 1 – 2 Months)
High-Efficiency HVAC.
Variable-speed heat pumps, dedicated ERVs, and in-slab hydronic loops are laid out to maximize comfort zones while cutting annual energy loads by 40–60 percent compared with baseboard heat.
Whole-House Electrification.
We can pre-run conduits for solar inverter hubs, dual EV chargers, and a future battery wall. Even if you don’t order the panels on day one, the infrastructure is ready when rebates or technology improve.Homeowner Walk-Throughs.
Blue painter’s tape marks art niches, towel bars, and smart-switch locations. Adjusting stud placement now avoids drilling into air barriers later, protecting airtightness and timeline.Interior Finishes & Custom Millwork (≈ 3 – 4 Months)
Proactive Allowance Management.
Clients choose flooring, tile, plumbing fixtures, and low-VOC paints before drywall starts. That early commitment lets us:
- Order Long-Lead Millwork. Locally built cabinetry is commissioned six months out. Finishes cure in the shop, not in your house.
- Sequence Trades Efficiently. Flooring installers follow painters within hours, not weeks, because materials are on site, climate-controlled, and ready.
- Create Early Punch Lists. Our team walks the site frequently, flagging minor dings so they don’t snowball into closing-day frustrations.
Sustainability is front-and-center: formaldehyde-free cabinets, recycled-content tile, and LED lighting packages slash embodied carbon and utility bills.
Exterior Finishes & Landscaping (≈ 1 – 2 Months, Overlapping)
Durable Cladding Systems.
Rainscreen, flashings, siding and exterior trims are installed carefully, encouraging downward drainage. The assembly can dry out after a West-Coast storm and easily meets Step Code moisture targets.
Permeable Hardscapes & Native Landscapes.
We specify permeable pavers or crushed-shell paths so rainwater recharges aquifers instead of overwhelming storm drains. Landscaping plans favour drought-tolerant Pacific Madrone, Oregon grape, and salal, cutting irrigation demands to near-zero after establishment.
Final Inspections, Occupancy & Handover (≈ 1 Month)
Municipal Final & Occupancy.
Inspectors verify structural compliance, fire-safety measures, and Step Code air-tightness via blower-door testing. We routinely hit 1.0 ACH@50 Pa or better - twice as tight as code minimums.
Stillwater Warranty Walk-Through.
We tour every space with you, note any paint touch-ups or hardware tweaks, and log them in our cloud portal. A one-year and two-year follow-up keep small issues from becoming expensive surprises.
Move-In Day!
You receive a digital homeowner manual with filter-change reminders, smart-thermostat and humidistat tutorials, and our direct service line. Annual performance reviews ensure your mechanical systems stay dialed in and your utility bills stay low.
Key Factors That Influence Your Greater Victoria Build Time
Weather & Seasonality
Greater Victoria’s wet autumns can turn excavation sites into mud pits, slowing heavy equipment and concrete work. Conversely, our mild winters usually let framing crews keep hammering through January. Planning earthwork for the drier shoulder seasons - and using temporary ground-source loops to cure slab heat instead of propane heaters - keeps the schedule tight while cutting carbon emissions.
Site Complexity
Steep slopes, bedrock close to grade, or tight urban infill lots require extra coordination. Rock blasting or anchoring footings to bedrock adds days, sometimes weeks, to the critical path. Whenever possible we design stepped or pier foundations that use less concrete and leverage the existing terrain, reducing both timeline risk, costs, and embodied carbon.
Municipal Review Queues
Post-pandemic staffing gaps mean your permit could sit an extra month if drawings bounce between departments. We counter this by submitting one comprehensive package that includes variances, heritage considerations, and environmental reports up front. A clean, well-documented application not only moves faster but also demonstrates that the project will exceed minimum code requirements.
Design Changes (Change Orders)
Every mid-build tweak ripples through trade schedules, procurement, and inspections - often adding one to three weeks and unexpected costs. Our pre-construction process explores details upfront so nearly all adjustments happen on paper, not on site, preventing timeline slips and material waste.
Supply Chain & Labour Availability
Custom windows, imported tile, and specialty trades can carry 12- to 16-week lead times. We favour Canadian-made windows, recycled-content tile, and local craft trades to shorten waits and cut freight emissions. Long-lead items are ordered as soon as designs lock, then stored until needed.
Energy Step-Code Targets
Aiming for tighter air-change rates or Passive House-level performance triggers additional blower-door tests and inspection checkpoints. While these steps add a few days, they pay dividends in lower operating costs and future resale value. We incorporate Step-Code details - continuous insulation, taped sheathing seams, HRV balancing - into the baseline design so they don’t become last-minute add-ons.
By anticipating these six factors and weaving sustainability into each solution, Stillwater keeps most custom builds on a dependable 15- to 24-month runway - while delivering a home that’s kinder to both your utility bills and the Island you love.
Proven Strategies to Accelerate Your Build
Choose a Local Team.
Because architects, estimators, and carpenters share the same project board as part of our integrated project delivery framework, questions get answered in minutes, not weeks.That tight feedback loop can shave a month off construction alone.
Submit One Comprehensive Permit Package.
Splitting variances, heritage items, or environmental DPs into separate filings stretches review timelines by default. We bundle them so municipal reviewers touch your file once, not three times.
Pre-Order Long-Lead Items.
Windows, air-source heat pumps, appliances, and custom millwork are ordered as soon as designs are locked. We store them so weather or factory delays don’t hold the site ransom.
Stay Plugged In.
Weekly site-walks and monthly budget snapshots mean you approve selections quickly, and we keep momentum. Decision paralysis is the silent timeline killer; our clear dashboards keep everyone tuned-in.
Embrace Digital Collaboration.
By using the latest technology, our project team can visualize your projects progress in real time - making it easier to spot and resolve potential conflicts to keep your project on track
Typical Custom Home Build Timeline Summary
Phase |
Average Duration |
Cumulative Time |
Planning & Design |
2 – 4 mo |
2 – 4 mo |
Permitting |
2 – 6 mo (parallel) |
4 – 10 mo |
Construction |
8 – 14 mo |
12 – 24 mo |
Most Stillwater clients move in 12–24 months after our first handshake - even on complex Gulf-Island builds. By front-loading design decisions, bundling permits, and ordering long-lead items early, the schedule stays predictable and the carbon footprint stays small.
Conclusion: Marathon, Managed, and Mindful of the Planet
A Greater Victoria custom home really can be delivered in under two years - and meet tomorrow’s sustainability standards - when every stage is mapped, measured, and managed. At Stillwater, we pair island craftsmanship with lean project-management discipline: transparent budgets, proactive permitting, long-lead procurement, and a warranty program that stays with you for a decade. Ready to turn West-Coast dreams into carbon-smart reality? Let’s talk timelines.
Book a complimentary Discovery Call and experience the Stillwater Difference